<Work> Element

For a <Task>, <Work> is the total amount of work scheduled to be performed on a task by all assigned resources.

For a <Resource>, it is the total amount of work scheduled to be performed by a resource on all assigned tasks.

For an <Assignment>, it is the total amount of work scheduled to be performed by a resource on a task.

For a <Baseline>, it is the scheduled work for the task, resource or assignment when the baseline was saved.