Show AllShow All

<TotalSlack> Element

The amount of time a task can be delayed without delaying a project's finish date.

ShowElement Properties

ShowParent Elements

ShowSee Also

©2003-2004 Microsoft Corporation. All rights reserved. Permission to copy, display and distribute this document is available at: http://msdn.microsoft.com/library/en-us/odcXMLRef/html/odcXMLRefLegalNotice.asp