<Start> Element

For a <Task>, <Start> is the date and time that a task is scheduled to begin.

For a <Resource>, it is the date and time that a task is scheduled to begin.

For an <Assignment>, it is the date and time that a task is scheduled to begin.

For a <Baseline>, it is the scheduled start date and time of the task, resource, or assignment when the baseline was saved.

For <TimephasedData>, <Start> is the start date and time of the timephased data period in the task, resource, assignment, or baseline.