Indicates whether the end of completed portions of tasks scheduled to have been completed before the status date, but begun late, should be moved up to the status date.
Property | Value |
---|---|
Data Type | Boolean |
Minimum Occurrences | 0 |
Maximum Occurrences | 1 |
Default Value | False |
Abstract | False |
Nillable | False |
Element Constraints | N/A |
You will experience a rounding error with this element. The internal work value has eight digits; it will lose .001 seconds for every minute, causing a rounding error.