<FinishVariance> Element

For a <Task>, <FinishVariance> is the amount of time that represents the difference between a task's baseline finish date and its current finish date.

For an <Assignment>, it is the difference between an assignment's baseline finish date and its scheduled finish date.

ShowElement Properties

ShowParent Elements

ShowSee Also