Show AllShow All

<Finish> Element

For a <Task>, <Finish> is the date and time that a task is scheduled to be completed.

For a <Resource>, it is the date and time that a task is scheduled to be completed.

For an <Assignment>, it is the date and time that a task is scheduled to be completed.

For a <Baseline>, it is the scheduled finish date of the task, resource, or assignment when the baseline was saved.

For <TimephasedData>, <Finish> is the finish date of the timephased data period in the task, resource, assignment, or baseline.

ShowElement Properties

ShowParent Elements

ShowSee Also

©2003-2004 Microsoft Corporation. All rights reserved. Permission to copy, display and distribute this document is available at: http://msdn.microsoft.com/library/en-us/odcXMLRef/html/odcXMLRefLegalNotice.asp