<ActualOvertimeCost> Element

For a <Task>, <ActualOvertimeCost> is the costs incurred for overtime work already performed on a task by all assigned resources.

For a <Resource>, it is the cost incurred for overtime work already performed by a resource for all assigned tasks.

For an <Assignment>, it is the cost incurred for overtime work already performed by a resource on a task.