Show AllShow All

<ActualDuration> Element

The span of actual working time for a task so far, based on the scheduled duration and current remaining work or percent complete. Actual duration can be calculated in two ways, either based on percent complete or remaining duration.

ShowElement Properties

ShowParent Elements

ShowSee Also

©2003-2004 Microsoft Corporation. All rights reserved. Permission to copy, display and distribute this document is available at: http://msdn.microsoft.com/library/en-us/odcXMLRef/html/odcXMLRefLegalNotice.asp